Proposed Sewerage System for Springfield, Mo.

Proposed Sewerage System for Springfield, Mo.

According to The Democrat of Springfield, Mo., the sewerage system adopted by the city council contemplates the construction of fifteen and a half miles of public sewers, about nine and a half miles of which will be within the city limits and will be what is known as pipe sewer, the pipe varying from eight to twenty-six inches in diameter. The remainder of the sewer will be located without the city, a considerable portion of it will be of brick.

The main sewer, from Main to Fort streets, 3412 feet, will be 24 x 36 inches. From Fort to Hawthorne streets, 5180 feet, will be 26 x 39 inches, and from the junction to the outlet, 4761 feet, w ill be 28 x 42 inches. The average depth of the main sewers will be six feet. On the north side the sewers outside of city limits to outlet below Doling’* Park, 12,175 feel in length, will be mainly pipe work of the average diameter of eighteen inches.

The total amount of material to be excavated ia the construction of this system will be about 94,268 cubic yards. Contractors and gentlemen of experience in public works estimate that the excavation of this amount of material will not cost exceeding $45,000, the cost of removing solid rock not to be greater than $1.40 per cubic yard. The twelve miles of sewer pipe can be purchased and delivered on the ground at a cost of not to exceed $21,500. The cost of laying the pipe, including cement, handling, etc., will be about $13,000. The cost of brick sewer, including all material, will not exceed $35,000. One hundred and sixty man-holes will average fortyone dollars each, or $6560. To these estimates may be added the engineering expense, incidentals etc., which should not exceed $8000,and we have a total of $t29,o6oasthc maximum cost of constructing the proposed system.

No posts to display